NUCOR STEEL —
SHUTDOWN SERVICES
Seattle, Washington

Service Provided
  • Phoenix Industrial has provided structural, mechanical and piping services during plant shutdowns for the past two years.
    Work included:
    • Installation of new hydraulic bundle bumper, new rails for two plate transfer conveyors, new dampers on the furnace inlet fan, and new cooling water splash guards on the ingot line
    • Fabrication and installation of new maintenance platforms, including stairway and handrail
    • Fabrication and installation of new rail car loading platform
    • Repair of structural members on the MCC building
Total Project Value
$200,000

Project Statistics
  • 3,000 man-hours
  • All work completed with no recordable or lost-time accidents
  • All work completed on time and within budget
Project Timeline
Start Date
  May 2004

Completion Date
  May 2006