- Project required pouring foundations for a new, grass-roots Spiral Tube Mill manufacturing facility. Building footprint was 260,000 square feet.
Work included:
- Installation of concrete foundations for two forming mills, surge tables, hydrostatic tester, x-ray
inspection tables, quench pits, transfer conveyors, and U-T inspection tables
- Formwork included both engineered form systems and lumber systems
- Installed more than 6,000 anchor bolts for mechanical equipment and 100,000 pounds of pre-fabricated metal embeds
- Poured 195,000 SF of 6" and 12" reinforced concrete slabs
- Poured more than 13,000 cubic yards of 4,000 PSI concrete for slabs and foundations
Total Project Value
$2,700,000
Project Statistics
- 40,000 man-hours
- All work completed with no recordable or lost-time accidents
- All work completed on time and within budget
Project Timeline
Start Date
December 2005
Completion Date
August 2006