- Phoenix Industrial provided structural, mechanical, piping and electrical services for expansion of mill production capabilities for silver mine
operation.
Work included:
- Supply and installation of more than 20 tons of structural steel for support platforms around column cells and float cells
- Set, leveled and aligned conveyor equipment for crusher, sampling station and cyclone
- Set, leveled and grouted two 6'-diameter x 75'-high column cells
- Set, leveled and aligned 24 floatation tanks
- Completed major installations while mill remained operational
- Completed all tie-in work during a seven-day shutdown. A total of 50 personnel worked around the clock to complete shutdown on time.
- Responsible for installation of all electrical
Total Project Value
$1,700,000
Project Statistics
- 12,000 man-hours
- All work completed with no recordable or lost-time accidents
- All work completed on time and under budget
Project Timeline
Start Date
September 2005
Completion Date
December 2005