- Phoenix Industrial provided civil, concrete, structural steel, mechanical, piping and electrical services to expand the existing zinc circuit process capabilities for Hecla Mining’s existing silver mine operation. The work included:
Work included:
- 500 cubic yards of concrete for new building and equipment foundations, along with elevated platform slab.
- Supply and installation of 450 tons of structural steel for building expansion and work platforms.
- Installation of zinc press, thickener tanks, column cells, rotating equipment and on-stream analyzer equipment.
- Supply and installation of 15,000 LF of large and small bore process piping, valves and fittings.
- Installation of new Motor Control Center.
Total Project Value
$5,000,000
Project Statistics
- 30,000 man-hours
- No recordable or lost-time accidents
- All work completed on time and within budget
Project Timeline
Start Date
April 2007
Completion Date
December 2007