Lafarge
Ash Grove
Hecla
Hecla2
- Phoenix Industrial modified the entire dust collection system for client's cement storage facility.
Work included:
- Removal of two existing baghouses located on top of 130'-tall concrete silos
- Installation of two new baghouse dust collectors
- Fabrication and installation of 10"-diameter dust collection pipe
- Installation of four, 10" rotary valves
Total Project Value
$250,000
Project Statistics
- 4,500 man-hours
- All work completed with no recordable or lost-time accidents
- All work completed on time and under budget
Project Timeline
Start Date
November 2003
Completion Date
December 2003