Thompson Falls, MT
GE Energy
- Responsible for mechanical and piping services for two annual plant shutdowns of a 75 MW gas-fired power facility
- Replaced twenty tube sections on LP Evaporator section of the HRSG
- Cut out and replaced existing 3.5" carbon steel tubes and replaced with 2.25" chrome material
- All welding was completed in accordance with ASME and NBIC codes. All welds passed x-ray inspection and no
rework required
- Replaced internal piping on the LP drum
- Replaced six steam-pressure release valves
- Installed 1" chrome drain line for 24" high-pressure steam pipe
- Installed four 1" drains and chrome piping for the condenser. All work was completed under Phoenix's R stamp
Total Project Value
$150,000
Project Statistics
- 2,000 man-hours
- All work completed with no recordable or lost-time accidents
- All work completed on time and within budget
Project Timeline
Start Date
May 2005
Completion Date
May 2006